1. According to the provisions of safe electricity consumption, turn on the power supply of the lighting line, and turn on the power supply and jog the host to see if it is running normally when the power is sent to the motor.
2. Water flow: according to the fuselage seat sign, the cooling water enters and the faucet is leaking, and the water flow is subject to the smooth inlet and outlet.
3. Air pump: connect the air pump to the air channel faucet, turn on the air compressor at the same time, and the air pressure can only be used when the air pressure reaches 0.2~0.4 MAP or more.
4. Refueling: Refueling is added to the box and gearbox. Note: Refueling is 2/3 of the oil volume in the box.
5. PVC plastic material bearing shaft, adjust the inner and outer cone nuts, run the mold to the next point, PVC plastic passes, and the back of the lead seat is opened and pressed, pay attention to the PVC plastic on the surface of the machine plate to the track shall prevail, both sides are equally uniform.